On august 18th the three full scale demonstration pylons are installed at Valmont SM in Denmark. The pylons are installed having a 330m span in real conditions according to EN 50341-2-4.
The demonstration pylons are installed including all required fittings and conductors. At the demonstration site the pylons are installed on 10m monopiles directly hammered into the ground – without concrete and time-consuming techniques. It only requires 20min to hammer a monopile of 10m.
Our installation procedure allows 3 pylons to be installed pr. Day / 1 km pr day.
Having conductors installed the demonstration project will be ready for inspection and presentation in the following months.